West End, Soho

case studies • Dilapidations • West End, Soho

The Project

PBC were appointed to prepare a schedule of dilapidations for this 5th Floor West End Office, located in the heart of Soho, London.

With the tenancy coming to an end, PBC acted on behalf of the landlord for this 3,311 sq ft commercial space:

1nternal Repairing & Insuring (IRI) Lease –5th Floor Office, West End (3,311 sq ft)

Original Claim – £144,983.60 (£43.79 per sq ft) With an Agreed Settlement – £130,594.37 (£39.44 per sq ft)

 

Timescale: Settled within four weeks of formal service
Client: Private

 

PBC Soho Dilapidations

 

See further dilapidation case studies here, and get in touch with our Building Consultancy team to assist you further here.

Client

Private

Property

West End, Soho

Role

Dilapidations

Contract Value

Undisclosed

Time Scale

4 weeks

Instructions

PBC were appointed to prepare a schedule of dilapidations for this 5th Floor West End Office, located in the heart of Soho, London.