It is now week 8 of the project, and works are progressing well. The green bean silo structure has been erected, new concrete hard standings are being laid and approximately 50% of the attenuation tanks have been installed. The piling ground improvement and foundations have also been installed. The steel structure erection and commencement of the cladding will start WC 4th January 2016. Further updates of progress will follow………