Following vacant possesion by the previous tenant, PBC were instructed as Project Manager and Employer’s Agent by Logicor to manage the six month refurbishment of a 300,000 sq. ft. distribution warehouse. The works entailed new concrete yard, new warehouse roof, cladding treatment and a full CAT A refurbishment of the office accommodation. This included a new rainscreen cladding system, new windows and doors. Amazon were secured as a tenant during the project and PBC managed the interface between the tenant and client to ensure early access and partial possession were achieved, to enable Amazon gain early access. The project was completed ahead of time in September 2015 and has added substantial value to the client’s asset.
What Our Client Has to Say
“We are pleased with the successful outcome of this warehouse refurbishment project”
Stephen Vickers| Director of Property | LOGICOR